thailand factory

JOINT RISK MANAGEMENT WITH OUR CUSTOMERS

Why we are investing 10 million USD in an additional facility. 

Proactive

Against labor shortage in modern-day China

More insights

Labor Shortage

Problems present in Modern Day China include labor shortage and an aging worker population, leading to a rapid increase in labor overhead.

Responsive

We want to be part of the solution for our customer's need of Geo-diversified sourcing.

Permitting

Foreseeing

Against uncertain political climate in the future

More insights

Political Climate

We are worried about a worsening trade war between China and US as well as potential geopolitical conflict with China & Taiwan.

thailand factory

Details about operations & facilities plans

facility

capacity

production

Team

FACTORY timeline

  • 2024 Q1

    purchase land

  • 2024 Q2

    design factory & install relative applications

  • 2024 Q3

    start construction of production facility

  • 2024 Q4

    construction continues

  • 2025 Q1

    Move in & test machineries. Train employees. Soft Open to trail production period

  • 2025 Q2 & Q3

    recruit more workers & start mass production to reach targeted capacity

  • 2025 Q4

    Adjust procedures and production capacity based on production needs

  • 2024 Q1

    purchase land

  • Q2

    design factory & install relative applications

  • Q3

    start construction of production facility

  • Q4

    construction continues

  • 2025 Q1

    Move in & test machineries. Train employees. Soft Open to trail production period

  • Q2 & Q3

    recruit more workers & start mass production to reach targeted capacity

  • Q4

    Adjust procedures and production capacity based on production needs